VERIFI® Sample Specification
SECTION 03300 - CAST-IN-PLACE CONCRETE
Metered Water Additions in Transit
Note to Specifier: ASTM C94/C94M was revised in 2013 to allow water additions during transit for trucks equipped with automated slump and water management systems. Check your specification to ensure it does not prohibit in- transit addition of water. Add the following text.
Water additions during transportation shall be made in accordance with ASTM C94/C94M.
Automated Quality Control and Quality Assurance
Note to Specifier:The following text defines minimum requirements for an automated slump management system for ensuring consistent quality concrete.
PART 1 - GENERAL
1.X Quality Control By Contractor
- Automated Slump Management System. Ready mix trucks shall be equipped with the VERIFI ® Slump Management System (GCP Applied Technologies, www.gcpat.com, 62 Whittemore Ave Cambridge, MA 02140) or equivalent system capable of the following:
- Monitor concrete slump to an accuracy of +/- 25 mm. The equipment shall obtain one or more physical measurements on the truck mixer related to concrete slump and provide an indication of slump based on pre- established correlations. Equipment shall be accurate for 50% to 100% of mixing drum volume capacity. Upon request, concrete supplier shall provide data no older than 24 months confirming the accuracy of calibration for each truck type.
- Meter water added to the truck to an accuracy of +/-3% of the amount added or +/- 1 liter, whichever is greater. Upon request, concrete supplier shall provide data no older than 12 months confirming the accuracy of calibration.
- Meter admixture added to the truck to an accuracy of +/-3% of the amount added or +/- 1 liter, whichever is greater. Upon request, concrete supplier shall provide data no older than 24 months confirming the accuracy of calibration.
- Monitor concrete temperature to an accuracy of +/- 1°C. Upon request, concrete supplier shall provide data no older than 24 months confirming the accuracy of calibration.
- Perform automated additions of water, admixture, or both to achieve a target slump.
- Stop additions of water when reaching the maximum water content for the mixture design.
- Provide the following via electronic means or visual display to an inspector upon request at the jobsite: concrete slump, concrete temperature, water added, admixture added, age, total revolutions, total revolutions at mixing speed since last water addition.
- Provide the following via electronic means to the engineer: concrete slump, concrete temperature, water added, admixture added, age, total revolutions, total revolutions at mixing speed since last water addition. All data shall be for the start of discharge.
gcpat.com.au | Australia customer service: 1800 855 525
We hope the information here will be helpful. It is based on data and knowledge considered to be true and accurate, and is offered for consideration, investigation and verification by the user, but we do not warrant the results to be obtained. Please read all statements, recommendations, and suggestions in conjunction with our conditions of sale, which apply to all goods supplied by us. No statement, recommendation, or suggestion is intended for any use that would infringe any patent, copyright, or other third party right.
VERIFI is trademark, which may be registered in the United States and/or other countries, of GCP Applied Technologies Inc. This trademark list has been compiled using available published information as of the publication date and may not accurately reflect current trademark ownership or status.
© Copyright 2024 GCP Applied Technologies Inc. All rights reserved.
GCP Australia Pty. Ltd., 14 Colebard Street West, Archerfield, Brisbane, Queensland 4108, Australia. This document is current only as of its stated date and applies to use in Australia only. Always refer to the latest information available at www.gcpat.com.au. GCP does not accept responsibility for information obtained from other sources. For further information or in the event of any conflict, contact GCP Customer Service.
Last Updated: 2026-04-29
https://gcpat.com.au/en-gb/solutions/products/verifi-sample-specification